Chiller maintenance checklist for a data-center plant: every item by interval, the state the chiller must be in, and the reading that proves it

Every checklist on page one lists the same chiller items on the same daily-to-annual cycle. None of them says which items need the chiller stopped, what has to be true of the plant before it is, or which reading on the chiller's own controller proves the item was done.

Design-partner scope23 min read

By Jeel Patel, Founder at HVAC Software

The annual on chiller 2 is booked for Thursday. The work order carries the manufacturer's annual inspection list, the plant is three chillers at N+1, and chiller 3's last oil sample came back with rising iron. Which of the items need chiller 2 stopped, and whether chillers 1 and 3 can carry the hall for the eight hours its waterboxes are open, is not written anywhere on the order.

A chiller maintenance checklist is the manufacturer's list of daily log readings, quarterly and semi-annual service items and an annual shutdown inspection, with a non-destructive tube test every three to five years and ASHRAE Standard 180 as the published floor. On a data-center plant every item also carries the state the chiller must be in to do it. Running items are readings from the controller and cost the plant nothing, stopped items cost the plant its spare for the length of the visit, and opened items add the EPA card and the lock. Every item closes on a reading from the chiller's own controller rather than on a tick.

  • The intervals are the manufacturer's guides, and the manufacturers say so. Carrier's 19XR manual calls its time intervals guides to service only, to be set on load, run hours and water quality, and ASHRAE 180 calls its Section 5 frequencies the minimum required for compliance.
  • A data-center chiller runs about 8,760 hours a year. Trane's first oil change falls at six months or 1,000 hours, whichever comes first, and at 24 hours a day the 1,000 hours arrive in about six weeks.
  • Roughly a third of the items need the chiller stopped, and the annual inspection needs it opened. Those are the items an N+1 plant has to gate behind a confirmed spare, because a second chiller out in the same window is how a PM becomes an incident.
  • Every item can be proven from the log: approach temperature against the new-unit baseline, oil differential pressure, discharge temperature, motor amps and, on a low-pressure chiller, the purge pump-out minutes. The work order should close on those readings.

What is a chiller maintenance checklist?

It is the list of readings, inspections, tests and cleaning tasks a water-cooled chiller receives on a fixed cycle, so that it fails less often and so that a developing fault is caught while the spare can still carry the load. A chiller is the plant's cold source, and every computer room air handler (CRAH) on its loop depends on it, which is why its list is longer and its shutdown costlier than any hall unit's. The list divides into what an operator reads every day, what a technician services every few months, and what a certified technician does once a year with the machine open.

Four documents set the intervals, and they do not agree with each other. The manufacturer's operation and maintenance manual is the binding one, ASHRAE 180 is the reference the sector cites, the EPA's refrigerant rules fix the leak-repair clock, and the site's own method of procedure (MOP) decides how a chiller is taken out of the plant and put back. The table below is what each of the opened documents actually says.

SourceDaily and weeklyMonthly to semi-annualAnnualLonger
Trane CenTraVac guide, Table 22 (CVHE-SVX02P-EN, 2019)Daily: evaporator and condenser pressure, oil tank, differential and discharge oil pressure against the normal table, oil level in the lower sight glass, and the log completedEvery 3 months: water strainers, vane linkage, tang and filter-valve O-rings, the purge drip-leg. Every 6 months: the evaporator refrigerant sensor if exposed to extremesShut the chiller down once a year for the Appendix D inspection list, the purge annual, the ice-bath sensor check, condenser tube inspection, an oil sample to a laboratory, motor winding resistance and a leak testEddy current test of condenser and evaporator tubes every three years, with a baseline before service
Carrier AquaEdge 19XR manual (PIC 5, HFC-134a)Weekly: oil level marked on the sight glass and observed while shut down, with any oil added logged by amount and dateNo fixed band. Intervals are guides set on load, run hours and water quality, with a Service Ontime counter reset after major serviceOil filter, refrigerant filter-drier, relief valve inspection, all eight pressure transducers, starter connections, condenser tubes cleaned at least once a year, and a yearly oil analysis and vibration readingOil changed within five years if no analysis is run. Oil reclaim filter, economizer float and damper valve every five years
YORK YK manual, Form 160.75-O1, Section 2Daily: displays, bearing oil pressure and level, condenser and chilled water in and out against design, saturation temperature, discharge temperature, motor current, and the condenser approach against the new-unit value. Weekly: refrigerant chargeMonthly: leak check the entire chiller. Quarterly: oil analysis. Semi-annually: oil filter element, oil-return dehydrator and eductor nozzle, controls and safety cutoutsOil drained and replaced unless the quarterly analysis says otherwise, water strainers, tubes and end sheets, motor cleaned, megged and lubricated, electrical components servicedEddy current test and tube inspection every two to five years, in the maintenance-requirements table
ASHRAE/ACCA Standard 180, Table 5-6 Chillers, water-cooled (2012 edition text)NoneWater chemistry monthly on an open system and quarterly on a closed one. Gearbox quarterly. Control system semiannuallyControl box, motor contactor, refrigerant pressures and temperatures, open drive alignment, fouling on heat exchange surfaces, fluid flow and leaks, compressor oil level and pressure, VFD, field-serviceable bearingsNone
Four sources, four bands. The daily log is the spine of the OEM lists and absent from the standard. The three-year tube test is absent from every checklist on page one but two.

The words that matter in those manuals are the ones about guides and minimums. Carrier tells the reader to establish a regular maintenance schedule based on your actual chiller requirements such as chiller load, run hours, and water quality, with the listed intervals offered as guides to service only. ASHRAE's 2018 errata restates clause 4.3.2.2 as the Section 5 frequencies being the minimum required for compliance. A plant that runs the manufacturer's annual once a year and nothing between is below both.

Why is a data-center chiller's checklist different from a building's?

A building chiller has a cooling season and an off-season, and the annual is done in the off-season with the machine cold and nobody depending on it. A data-center chiller has neither. Kaltra's checklist is the one page-one result that says so, in a clause: inspect twice a year for seasonal use and four times a year in continuous operation. The load does not fall in January, and there is no afternoon on which the plant can lose a chiller for free.

The manufacturers write some intervals in hours, and hours arrive faster on a plant that never stops. Trane's guide sets the first oil and filter change at six months of accumulated operation or 1,000 hours, whichever comes first, and at 24 hours a day 1,000 hours is about 42 days. A building reads that sentence as six months. A data center reads it as six weeks, and should read every calendar interval in the manuals with the same arithmetic in mind.

On a building the checklist is a list of tasks with a season to do them in. On a data-center plant it is a list of tasks, each with a question in front of it: can the plant spare this chiller right now?

Standard 180 points the other way for buildings. Its 2012 text gives the example of an old chiller retained as a backup whose inspection may be adjusted to reflect fewer operating hours, which is a relief a data-center spare cannot take, because a rotated N+1 chiller runs the same hours as the duty machine and carries the hall the moment one is stopped. The Uptime Institute's own explainer names chillers among the redundant components a Tier II site holds for select maintenance opportunities, and defines a Tier III site as one that requires no shutdowns for equipment replacement and maintenance. Which of those two sentences describes the plant decides whether a stopped-chiller item is a task or a risk.

What is on the checklist, daily to every three years, and what proves each item?

The table below is the list, assembled from the Trane, Carrier and York manuals and ASHRAE 180's Table 5-6, with the interval each source gives. Two columns are added to what any of those documents carries: the state the chiller has to be in to do the item, and the reading on its own controller that proves the item afterwards.

Running means the log is read with the machine on, and stopped means the compressor is off with the refrigerant in place, so the plant is carrying the hall on N. Opened means the refrigerant circuit or a waterbox is open, which adds the EPA card and the lock.

ItemInterval and sourceChiller stateThe reading that proves it
Read and record evaporator and condenser pressure, saturated temperature, entering and leaving water on both bundles, and the approach on eachDaily (Trane Table 22, York Section 2); a permanent record throughout each 24-hour period (York)RunningCondenser approach within the new-unit difference, and Trane's normal pressures for a low-pressure machine, 6 to 9 psia evaporator and 17 to 27 psia condenser
Read oil tank pressure, differential oil pressure, discharge oil pressure, oil sump temperature and oil levelDaily (Trane, York); weekly oil level while shut down, any addition logged (Carrier)Running for the readings, stopped for Carrier's weekly mark on the sight glassOil differential in Trane's 18 to 22 psid normal range, level visible in the lower sight glass while operating, and the amount and date of any oil added
Read compressor discharge temperature, motor current or percent RLA per phase, and starts and running timeDaily (York, Trane log sheet)RunningDischarge under York's 220 °F (104 °C) limit, amps balanced and inside the last month's band at the same load
Read purge pump-out minutes, on a low-pressure chillerDaily 24-hour and 7-day average on Trane's log sheet, with a site limit set from a one-week baselineRunningMinutes at or under the site's Daily Pumpout Limit, no limit alarm, and no drift against the same chiller's history
Check the refrigerant charge, and the purge sight glass and moisture indicatorWeekly (York charge check; Trane purge guide sight glass)RunningLevel in range, refrigerant flow visible in the purge sight glass, indicator dry
Leak check the entire chiller, and calculate the leak rate on any refrigerant additionMonthly (York); at the annual, and whenever the purge runs often (Trane); on every addition (40 CFR 84.106 for an HFC or HFC-blend chiller)RunningNo detector hit, a leak-rate record under the applicable threshold, and on a low-pressure machine the pump-out minutes inside the normal region
Clean the water strainers on both circuitsEvery 3 months (Trane); annually (York)Stopped, with the water side isolatedWaterside pressure drop across each bundle and the flow-switch status back to the pre-visit value
Lubricate the vane control linkage, ball joints and tang O-rings, and stroke the inlet guide vanesEvery 3 months (Trane); annually on the inspection listStopped for the linkage, running for the strokeIGV position tracks the command through the full range on the controller
Send a compressor oil sample to a laboratory for moisture, acid and wear metalsQuarterly (York); annually after the first change (Trane); yearly (Carrier)Running, from the sample valve beside the oil filterThe report on file, trended against the last one, and an oil change only where it says so
Change the oil filter element and the oil-return dehydrator, and check the eductor nozzleSemi-annually (York); yearly or when opened (Carrier)Stopped, compressor off and its disconnect open, with the filter isolated so the refrigerant stays in the machine (Carrier)Oil differential pressure back in range and the oil-return system returning oil on restart
Test the controls and safety cutouts, and verify the evaporator refrigerant temperature sensorSemi-annually (York); every 6 months if the sensor sees extremes and annually by ice bath (Trane); controls semiannually (ASHRAE 180)Running, with each test raising a controlled alarmEach trip in the alarm history with a timestamp, and the sensor within tolerance at 0 °C
Inspect the condenser tubes for fouling and clean themAnnual inspection, clean if fouled (Trane); rotary-clean at least once a year (Carrier); inspect and clean as required (York); fouling annually (ASHRAE 180)Opened at the waterboxes, water side drainedCondenser approach back to the new-unit difference at the same load and flow
Inspect and clean the evaporator tubesNormally every three years on a closed circuit (Trane); at the end of the first season then as the tubes dictate (Carrier)Opened at the waterboxesEvaporator approach back to baseline, and chilled-water delta-T at design flow
Meg the motor windings, inspect starter or drive contacts, re-torque connections, clean the drive's coolingAnnually (Trane Appendix D, York, Carrier); control box and contactor annually (ASHRAE 180)Stopped, starter isolated and locked out, capacitors discharged and verified per NFPA 70E (Trane)Insulation resistance trended against last year, and amps balanced per phase on restart
Inspect the relief valves and vent piping, recalibrate the pressure transducers, change the refrigerant filter-drierAt least once a year for each (Carrier)Stopped, with the affected line isolatedTransducers agree with a gauge, and the moisture indicator stays dry after the change
Service the purge: control checks, panel, and change the purge filter-drierAnnually (Trane purge guide), with the semi-annual coil and insulation inspectionRunning, with the purge isolated from the chiller at its valvesPump-out minutes return to the baseline after the change, not above it
Eddy current test the condenser and evaporator tubesEvery three years, against a pre-service baseline (Trane); every two to five years (York)Opened at both waterboxes, water side drainedThe test report against the baseline, and any plugged tube recorded on the asset
Inspect the compressor bearings and gearsWhen the annual oil analysis and vibration readings say so (Carrier); a complete teardown by the OEMOpened, refrigerant recoveredVibration signature and wear metals back to baseline on the next sample
Eighteen items, three states. Seven are readings the operator takes with the machine on. Six stop it. Five open it, and those are the ones that cost a maintenance window and a card.

York's maintenance-requirements table ends with a footnote worth keeping: the certified-technician items must be performed at the specified interval by an industry-certified technician, and a record of the procedure being carried out must be kept on file by the owner should proof of adequate maintenance be required for warranty. That is the manufacturer saying the tick is not the record. The reading column above is what a record should contain.

Carrier's manual shows how much of that record the controller already keeps. Its Service Ontime counter is to be reset to zero by the service person or the operator each time major service work is completed, so that the time between service events can be tracked, and Trane's log sheet carries the purge pump-out minutes for the last 24 hours, the last seven days and the life of the purge. A counter reset without the work, or the work without the reset, is the kind of disagreement a PM record exists to catch.

Which readings on the daily log say a chiller needs work before the calendar does?

The daily log is the front of the checklist, not a chore that precedes it. York's manual asks for a permanent daily record of temperatures and pressures at regular intervals throughout each 24-hour operating period, and says that readings taken when the system is new establish the normal conditions later readings are compared with. Every manufacturer opened for this page gives at least one threshold for that comparison, and the table below collects them.

ReadingWhat a drift meansThe threshold, and whose it is
Condenser approach: saturated condensing temperature minus leaving condenser waterFouled condenser tubes, wrong condenser water flow, or air in a low-pressure machineYork: must not exceed the difference recorded for a new unit by more than 4 °F (2.2 °C). Carrier: more than the design difference means dirty tubes or wrong flow. Trane: higher than predicted indicates fouling
Evaporator approach: leaving chilled water minus saturated evaporator temperatureEvaporator fouling or low refrigerant levelCompared with the new-unit value in every manual, with no fixed number given
Condenser pressure at a given loadFouling or non-condensables. Carrier notes that HFC-134a is a high-pressure refrigerant, so air usually does not enter that chillerTrane: 17 to 27 psia on a standard condenser, low-pressure refrigerant
Oil sump differential pressureFilter loading, pump wear or low levelTrane: 18 to 22 psid normal
Oil levelOil lost to the refrigerant side, or returned from itTrane: visible in the lower sight glass while operating. Carrier: marked and observed weekly while shut down
Compressor discharge temperatureHigh head, low charge or a lubrication problemYork: should not exceed 220 °F (104 °C) in normal operation
Purge pump-out minutes, 24 hours and 7-day averageAir leaking into a chiller that runs below atmospheric pressure. The split between chiller-on and chiller-off minutes points to the high or low sideTrane: about 7 minutes a day on average for a one-week period, varying widely by size and duty. Set a site limit from a week's baseline, high enough to avoid nuisance trips and low enough to alarm on a sudden rise
Motor amps and percent RLA per phaseLoad change, imbalance or a starter faultBalanced per phase and inside the last month's band at the same load, per the three OEM daily lists
Eight readings, one comparison each. The baseline is the chiller's own first month, which is why a plant that never took one has nothing to compare against.

The purge row deserves its own arithmetic, because it turns a daily reading into the leak-rate figure the regulation wants. Trane's guide gives the formula: percent annual leakage rate equals daily purge minutes times 0.0001 pounds of refrigerant a minute, divided by the initial charge, times 100, and it tells the operator to leak-check at the earliest convenience in the small-leak region and immediately in the large-leak one. The purge guide adds the reason the number is worth trending: the daily pump-out time indicates how the hermetic integrity of the chiller compares to historic pump-out times for the same chiller, and frequent filter-drier changes on the purge can indicate significant air or tube leaks.

Carrier gives the high-pressure equivalent as a rule rather than a reading. Its manual says ASHRAE recommends that a chiller be taken off line immediately and repaired if the refrigerant leak rate for the entire chiller is more than 10 percent of the operating charge per year, and Carrier itself recommends repairing leaks above 0.1 percent a year at the annual or whenever the refrigerant is transferred. Ten percent is also the legal threshold, and the section below says which rule carries it for which refrigerant.

Which items need the chiller stopped, and what has to be true of the plant first?

Eleven of the eighteen items stop or open the machine, and the annual inspection is the largest of them. Trane's Table 22 says to shut the chiller down once each year to check the items on its annual inspection list, and both Trane and Carrier put the electrical work behind a lockout: Trane's warning is to disconnect all power including remote disconnects, discharge the capacitors, verify with a meter rated per NFPA 70E and follow proper lockout and tagout procedures, and Carrier's is to shut off the chiller and open and tag all disconnects before working on any starter. On a building that is an electrical decision. On a plant it is a redundancy decision first.

The plant's N is the number of chillers the hall needs at its present load, and the arithmetic of the spare decides whether a stopped chiller is a task or an exposure. Uptime's Tier III definition is the sentence a stopped-chiller work order has to satisfy: every component needed to support the IT load can be shut down and maintained without impacting IT operations. On a Tier II plant, with redundant components but one distribution path, the same item is one of the select maintenance opportunities, and the window is the whole hall's.

  • Confirm the spare is ready, not just present: in automatic, no active alarm, no manual override, its own daily log clean, and start-tested since its last PM. A spare with a rising-iron oil report is not the spare it was last quarter.
  • Confirm the hall's load against N with this chiller stopped, at the condenser water temperature the plant will actually see that day, and with any other chiller already down or derated.
  • Take a baseline before the machine is touched: every reading in the daily-log table, the chilled-water supply temperature and delta-T at the plant header, and the inlet temperatures in the rows the loop serves.
  • Isolate under the site's written energy control procedure. 29 CFR 1910.147 requires procedures developed, documented and utilized for the control of hazardous energy, and the lock comes off only by the employee who applied it.
  • Do the stopped and opened items in one visit, so the chiller comes out of the plant once per cycle and not four times.
  • Restart under the manufacturer's sequence, return the chiller to its place in the staging order, and put the spare back to standby.
  • Watch the plant through the pull-down against the ASHRAE limit of 5 °C in any 15 minutes at the inlets, and close the work order when the post-visit readings match the proof column, not when the last box is ticked.
The two groups are the two prices. Reading costs nothing. Stopping and opening cost the spare, and the second group also costs a card and a lock. The proof node reads. It never starts, stops or stages a chiller.

The reason the gate is stricter for a chiller than for a hall unit is what a stopped chiller does to the time the hall has. A CRAC out of rotation costs one unit's airflow. A chiller out of the plant costs every CRAH on its loop their cold source the moment the remaining machines cannot hold the header, and the ride-through the hall then has is the water in the pipes and whatever storage the plant was built with. The pull-down after restart is bounded the same way, by ASHRAE's 5 °C in any 15-minute period at the IT inlet.

One chiller at a time
Eighteen items, eleven with the chiller stopped or opened. The eleven are one visit, one redundancy decision and one lock, or they are four of each.

Which leak-repair rule and which EPA card does your chiller's refrigerant put it under?

The refrigerant rows depend on what the chiller holds, and page one gives one answer for every chiller. The EPA's Emissions Reduction and Reclamation rule put appliances charged with an HFC, or a substitute with a global warming potential over 53, under leak-repair requirements at 15 pounds and up, from January 1, 2026. The older rule, 40 CFR 82.157, has applied since April 2020 only to appliances with 50 or more pounds of a class I or class II refrigerant, and the agency's fact sheet adds that appliances using a substitute with a GWP of 53 or below are not covered by the leak-repair requirements at all. Which of the three a chiller sits in is decided by its nameplate.

RefrigerantPressure class and EPA Section 608 cardLeak-repair ruleThreshold and clock
R-123 (HCFC, class II)Low-pressure appliance under 40 CFR 82.152, so Type III to open the circuit40 CFR 82.157, because it is a class II substance and Part 84 excludes appliances holding solely an ozone-depleting substance50 pounds or more of charge, 10 percent a year, 30 days to repair
R-134a (HFC, GWP 1,430 on EPA's table)High-pressure appliance, so Type II40 CFR 84.106, from January 1, 202615 pounds or more, 10 percent a year, 30 days, an initial and a follow-up verification test, and an annual leak inspection while over the rate
R-513A (HFC blend, GWP 630)High-pressure appliance, so Type II40 CFR 84.106, from January 1, 2026The same as R-134a
R-514A (substitute, GWP 3)Low-pressure appliance, so Type IIIOutside 84.106 leak repair, because its GWP is at or below 53No federal leak-rate threshold. The OEM's purge and leak-check items still apply
R-1233zd(E) (substitute, GWP 4)Low-pressure appliance, so Type IIIOutside 84.106 leak repair for the same reasonNo federal leak-rate threshold. The OEM's purge and leak-check items still apply
Five refrigerants, three rules. The 50-pound figure that page one gives for every chiller belongs to the first row only.

The card follows the pressure, not the rule. 40 CFR 82.152 defines a low-pressure appliance as one using a refrigerant with a liquid-phase saturation pressure below 45 psia at 104 °F, with R-123 as its example, and 82.161 requires anyone who maintains, services or repairs a low-pressure appliance to be certified as a Type III technician. A chiller on R-514A or R-1233zd(E) is outside the leak-repair rule and inside the certification rule at the same time, and which cards the person on shift actually holds is a record on the site, not a job title. The GWP figures in the table are from EPA's own reference table.

What the new section asks of an R-134a or R-513A plant is a set of records, each of which is a checklist row. The leak rate is calculated every time refrigerant is added, so every top-up on the work order carries a rate against the full charge. A rate over 10 percent starts a 30-day repair clock with two verification tests, the second after the chiller returns to normal operating characteristics, and an annual leak inspection until a year of calculations shows the machine under the rate. The full charge on the order comes from the nameplate or the methods 84.102 lists, not from memory.

What do the chiller controller, BMS, DCIM and CMMS already hold about a PM?

Each of them holds one column of the checklist table, and none of them holds the join between the item, the state the plant is in, and the reading before and after. The gap is not that the systems fail to communicate. It is that the PM record lives in the one system that never sees the log.

The chiller controller (Trane's Tracer AdaptiView, Carrier's PIC 5, York's OptiView)
Every reading in the daily-log table, the alarm history, the Service Ontime or run-hours counter, and on a low-pressure machine the purge pump-out minutes for 24 hours, 7 days and the life of the purge. Not whether the plant can spare the chiller, and not a before-and-after across a visit.
BMS
The trend of every point the controller exposes, the plant header temperatures and flows, and each chiller's status and staging order. Not the checklist, the interval, or which item a change in a trend belongs to.
DCIM
The hall's load, the installed plant capacity and therefore N. Nothing inside the chiller.
CMMS or EAM
The PM schedule, the item list, the parts, the technician, the oil report as an attachment, and the tick. Rarely a single point value on a closed order.
The MOP
The written sequence for taking the chiller out of the plant and putting it back. Not the live state on the day.

Standard 180 quietly allows the join. Its 2012 text says inspection may include data provided by sensors or a building management system, and that if unacceptable condition indicators are found on two successive inspections the owner shall investigate, while three successive acceptable inspections allow the frequency to be reduced and documented. A plant that closes each PM on a reading has that two-and-three history for free. A plant that closes on a tick has nothing to reduce or investigate from.

How to turn the checklist into a work order that closes on a reading this week

The table above becomes a site document in one afternoon per chiller model, and it changes what a closed work order means. The steps are in the order a plant lead would actually do them.

  • Copy the manufacturer's list for each chiller model you run, keep its intervals, and add the two columns: the state the chiller must be in and the reading that proves the item. Where your model's manual has no interval, use the nearest OEM band above and note the source.
  • Re-read every hours-based interval at 24 hours a day, and every calendar interval against the continuous-duty clause, before you copy it. Write the result on the order, not the manual's number.
  • Mark the stopped and opened items and group them into one visit per chiller, so each machine leaves the plant once per cycle.
  • Write the plant gate as three lines at the top of every stopped-chiller order: spare ready in automatic and start-tested, load against N with this chiller out at the day's condenser water temperature, and any other chiller already down.
  • Take the first-month baseline for every chiller that has none, from the controller's log, and store it on the asset. Without it the approach rule has nothing to compare with.
  • For every chiller, write the refrigerant, the full charge from the nameplate, the pressure class and card, and the leak-repair rule that follows from the refrigerant table above. Add the leak-rate calculation as a mandatory field on any addition.
  • On a low-pressure chiller, set the purge daily pump-out limit from a week's baseline and log the 24-hour and 7-day figures as daily items.
  • Close the order only when the post-visit readings sit inside the proof column, and hold it open when they do not.

What closes a chiller PM item is a reading that agrees with the tick. The tube clean shows as the condenser approach back at the new-unit difference, the oil change shows as the next laboratory report, the electrical work shows as balanced amps on restart, and the purge service shows as pump-out minutes back at the baseline. A visit that leaves none of those behind was a visit, not a maintenance record.

Loop 2E · rack inlet°C · 48 min
28262422Baseline bandWork reported complete03:1404:02
Closure conditions3 of 4
Δp holds ≥ 0.7 bar34 min elapsed · window satisfied
Rack inlet back in band14 of 14 racks within baseline band
Engineer confirms causeStrainer blocked upstream of CDU-2E
No recurrence in 24 hWindow still open · 6 h 12 m remaining
Incident stays open.Three of four conditions met is not recovery. The work order is complete; the incident is not.
The proof column, drawn: the layer reads the log before and after each item and holds the work order open until the reading agrees

What this cannot do

A checklist assembled from three manufacturers' manuals is not your chiller's manual. The intervals here are the ones those documents give, Trane's normal pressures are for a low-pressure machine, York's approach rule compares with the new-unit value rather than a fixed number, and the refrigerant rule is the regulation as it stands on the eCFR this month. The Thursday scene on chiller 2 is a composite assembled from those lists, not a site. Your model, your refrigerant and your site's reading of the lockout procedure decide the rest.

Nothing here takes control of a chiller or a plant. A decision layer that reads the log can say that the spare is in alarm and the order should not release, or that the Service Ontime counter was reset while the condenser approach never moved, and it does not start, stop, stage, isolate or reset anything. A named human stops the chiller, a named human applies the lock, a certified technician opens the circuit, and the layer records what was read before and after and whether the two agreed.

Answered

How often should a data-center chiller be serviced?

On the manufacturer's cycle, read at 24 hours a day. Trane's CenTraVac guide runs daily, every three months, every six months and an annual shutdown, York's YK manual runs daily through annual with a monthly leak check and a quarterly oil analysis, and Carrier sets its intervals on load, run hours and water quality. Kaltra's checklist puts continuous duty at four inspections a year against two for seasonal use.

What is included in a chiller maintenance checklist?

A daily log of pressures, temperatures, approach, oil and motor readings, a weekly charge check, a monthly leak check, quarterly to semi-annual oil analysis, filter and dehydrator changes and safety tests, and an annual shutdown for tube inspection and cleaning, oil, motor insulation, starter, relief valves and transducers. Water-cooled chillers add an eddy current tube test every three to five years.

Can you maintain a chiller without shutting down the data center?

Yes, one chiller at a time, behind a confirmed spare. About a third of the items stop the machine and the annual inspection opens it, and a plant gates those behind three checks: the spare is ready in automatic and start-tested, the hall's load is below N with this chiller out, and no other chiller is already down. Uptime's Tier III definition is exactly a site where every component can be maintained without impacting the IT load.

What is chiller approach temperature and what should it be?

Approach is the difference between the refrigerant's saturated temperature in a bundle and the water leaving it. The manuals compare it with the chiller's own new-unit value rather than a fixed number: York says the condenser approach must not exceed the difference recorded for a new unit by more than 4 °F, and Carrier and Trane both read a rise above the design or predicted value as fouled condenser tubes or wrong water flow.

How often should chiller tubes be eddy current tested?

Every three years in Trane's CenTraVac guide, with a baseline test before the chiller enters service so later reports can be read against it, and every two to five years in York's maintenance-requirements table. The test needs both waterboxes open and the water side drained, so on a data-center plant it is an opened-chiller item done inside the annual window, not a separate outage.

Does the 50-pound refrigerant rule apply to a chiller?

Only to a chiller on an ozone-depleting refrigerant such as R-123, under 40 CFR 82.157. A chiller on R-134a or R-513A holding 15 pounds or more has been under 40 CFR 84.106 since January 1, 2026, at 10 percent a year with a 30-day repair clock and two verification tests. A chiller on R-514A or R-1233zd(E) is outside the leak-repair rule because EPA lists both at a GWP under 53.

What proves a chiller PM item was actually done?

A reading on the chiller's own controller that moved the way the item should move it. A condenser tube clean brings the approach back to the new-unit difference at the same load, an oil change shows in the next laboratory report, electrical work shows as balanced amps on restart, and a purge service brings the pump-out minutes back to the baseline. The tick on the work order proves that someone ticked it.

Data centerRun data-center cooling as an operation, not an alarm feed.